New steel qualities, customer-specific applications, continuous improvement of steel properties, production of grades with excellent purity, energy and resource-saving processes – the aims of our innovation efforts are ambitious. Such extensive quality leadership can only be achieved by continuous investment so that each facility is
always state-of-the-art.

Blast furnace 5
Investment of 14 million Euro to reduce CO2 emissions and to create the conditions for green hydrogen to be used in practice, 2020
More
Steelmaking plant
100 million euros investment to complete the new continuous casting system S1, 2018 - 20019

Blast furnace 4
New lining, 2016

Steelmaking plant
New secondary metallurgy New casting ladles, 2013 and 2016

Rolling mill Völklingen
Expansion to create a bar steel centre New continuous blooming line, 2010 - 2016

Rolling mill Burbach
Extension of the roughing mill by 2 rolling stands, 2016

Rolling mill Neunkirchen
Revamping of line 32 with new loop and new wire rod outlet, 2016
- Work to complete the new continuous casting system S1 is on schedule
- 30 million euro investment completed – New continuous blooming line successfully put into operation
- Saarstahl invests around 30 million euro in the wire rod mill at the Neunkirchen location
- Drahtwerk St. Ingbert puts new surface treatment plant into operation - Investment of 13.5 million euro in state-of-the-art technology
- Saarstahl invests 46 million euros in modernisation of rolling mills